What are the construction requirements for on-site packaged boxes? Besides the construction team, let's learn about the construction requirements for packaged boxes on-site.
All connecting bolts between parts must be tightened.
Chalk line layout: Measure based on the position indicated in the residential area floor plan.
Bolts should be correctly installed according to design requirements, and washers must be laid and installed.
The installation positions of all parts of the on-site container must comply with design requirements, and on-site welding parts must be accurate with no temporary welding.
During on-site welding and transportation, areas where the primer has peeled off should be reapplied with anti-rust coating. Apply two coats of topcoat on exposed parts of the components. There should be no paint leakage, peeling, or issues with the paint and anti-rust coating.
Packaged box offices and walls must be modified according to the layout diagram. The corners and exterior corners of umbrella walls should be closed with square aluminum, and board-to-board connections should use I-shaped aluminum connectors. Each wall must be vertical, with consistent embedding depth, and must be cleaned carefully.
Additionally, the materials for the packaged box housing, wall columns, and others should be durable and meet load-bearing requirements. Materials explicitly prohibited by relevant authorities must not be used in packaged boxes. The overall structural load-bearing capacity and stability of the packaged box manufacturer must meet the requirement of remaining unaffected during invasion. Furthermore, the installation company must strictly follow the installation and operation manual for installation. Each procedure must be self-checked and recorded. If a procedure fails the inspection, the next installation procedure cannot proceed. The usage company must perform a comprehensive inspection, which must be approved and signed by both parties once it passes. At the same time, the number of occupants in each dormitory must not exceed 8 people.